28 September 2018

The Village is built from the ground up

The construction works

Construction works on the Village Landais Alzheimer, which started on 30 April 2018, is underway. Now that the levelling, foundations, insulation and paving have been completed, the first homes are being built in two of the four future neighbourhoods.

 

Construction progress at the end of September 2018

 

Since the preliminary works (installation of networks, building of roads) was completed by CASTILLON TP and BAUTIAA TP this summer, the companies DAUDIGEOS SAS and SEG FAYAT SASU have been able to start work on the four neighbourhoods. The stages of construction are as follows: excavations, foundations, filler stones, floor insulation, then casting of concrete slabs. The first homes to be built now have cast-in place-walls. The village is beginning to take shape.

In October, construction of the Bastide - the heart of the village - will start with the laying of the foundations.

 

 

The formwork is moved with a crane to help with the casting in place of the concrete walls.

 

©Dpt40/Sébastien ZAMBON

Formwork in specific shapes for the arches of the Bastide have arrived at the construction site.

©Dpt40/Sébastien ZAMBON

 

 

The neighbourhoods are arranged around the pond, which has been preserved throughout the works.

 

©Dpt40/Sébastien ZAMBON

 