Construction progress at the end of September 2018
Since the preliminary works (installation of networks, building of roads) was completed by CASTILLON TP and BAUTIAA TP this summer, the companies DAUDIGEOS SAS and SEG FAYAT SASU have been able to start work on the four neighbourhoods. The stages of construction are as follows: excavations, foundations, filler stones, floor insulation, then casting of concrete slabs. The first homes to be built now have cast-in place-walls. The village is beginning to take shape.
In October, construction of the Bastide - the heart of the village - will start with the laying of the foundations.